It looks like the de-jacking of the arch supports on the west stand has started. This is quite a long process, so don't expect the temporary structures to disappear quite yet.
Work under the east and west stands is going well.
Window frames being installed in west stand and chalk is being used to build up the levels in order to form the foundation concrete before the terracing is cast.
Insulation being put on back of west stand.
Final brick cladding started at the bottom of the north stand wall.
















--------------------------------------------------------------------------------