Same shot month by month

Progress from December 2009 to September 2010

24th September 2010

Forecast was rain approaching, so went to the Cathedral of Football early this morning.
West stand cladding and glass near completion.
North Stand wall at the top of the terracing has been rendered whilst the outside blockwork nears completion too.
The concourse approach to the West Stand entrance is being formed, and a huge pile of chalk has been excavated, ready for removal.
The new footbridge has been put across the railway lines, and bits are being built to join up with this.
If you've seen the 1901 Club DVD, you can see how everything is coming to reality.
What with the progress on the Amex, and being 2nd in table on goal difference, don't it make you feel good?

17th September 2010

What a lovely morning. Should I consider going to see Pope Benedict who is currently visiting our country? Certainly not when it's Friday and Falmer is there to be photographed. Anyway, I'm not even Catholic!
G.O.S.B.T.S virtually finished on East Stand, and progressing on West and now South Stands.
The extra long lorry in the site office car park has pieces of the new railway foot bridge on it, ready to be put in situ over this weekend.
The struts etc to receive this are already in place (see latter photos).
South Stand block work underway, and North Stand block work nearing completion.
West Stand terracing being caste.
Pitch area is having the temporary crushed brick layer removed, meaning that soon we will see the pitch being constructed.
Stunning mirror glass over main entrance to West Stand, and other glass there being installed.
Road works taking shape outside Stanmer Park. The east end levels are virtually built up to meet the A27/A270.