12th June 2009





Due to popular demand, 2 lots of photos again this week, 25A & 25B.

Spoke to a site manager today.
The grey stuff on the pitch area is crushed brick.
This is only temporary as the heavy plant which will be working from this area can't operate on a surface of wet chalk. It will be removed before the pitch construction gets under way.
The cement mixer is tipping concrete in the east stand foundations. This is now 70% complete, and when finished will be left to cure for a short while before the steel arrives.
The steel is all ready for shipment, and should arrive in the next two weeks.
The site offices etc have flown north for the summer as this area should have it's final layer of tarmac put down next week.