2nd October 2009

Bit of an autumn nip in the air this morning.
South stand growing by the hour.
I like the beautiful way the struts curve, almost scrolling across.
Lots of trees being pruned in the newly boarded off area.
After a couple of weeks of not much to see, it's really going made now.


30th September 2009

Demolition Special

Bungalows completely gone already
Miles of new security hoarding being erected right down to the footbridge at Falmer station.
Some previous angles for photos now impossible.
Time for some devious thinking!


25th September 2009

North east corner having reinforcing rods put in.
South stand foundations coming along.
2 specialist asbestos removal vans in the car park, ready for next week when the "soft" removal starts in the Uni buildings.
Natterjack tells us that the bungalow buildings will be the first to go, and the week after next should see some actual demolition.
First we couldn't wait for the diggers, then the steel, now the demolition.
In just over a week, according to John on the gate, there will be real visible progress.



18th September 2009

I've tried to vary it a bit this week.
It's another two weeks before Buckingham take over the Uni buildings.
The Costa Express has visited a new ground!
There's also a "Spot the Natterjack" competition, as site engineers wait eagerly to start demolition of said Uni buildings!!
Service works have started on the SEEDA stuff between Coldean Lane and Stanmer Park.


15th September 2009

From Inside the Building Site by Natterjack

11th September 2009

Not too much obvious visual change again this week, but expect all sorts in 2 weeks time when the Uni buildings start to get demolished.
It was easy to get access in to these buildings this week as they're being emptied, so I was able to take a couple of shots from the top floor corner window.
Most of the workforce seemed to be congregated at the north end of the east stand for some reason?


8th September 2009

Inside the ground by Natterjack