4th September 2009

Most work this week has been putting the "rebar" reinforcement mesh on to the floors of the east stand.
The terrace construction is coming along slowly but surely.
The big "flea-comb" thing has had the shuttering removed to expose the concrete.
There are several skips around the soon to be demolished buildings full of Joca files, and other redundant office type stuff. If you need anything of that nature, you may wish to nip round a bit quickish? (Hard up students?).

28th August 2009

Lots of action on the foundations of the south stand.
Terracing being built at the foot of the east stand.
Blue shuttering is put in place and concrete poured in, a whole 100m long step done in one go.
When it's set, they move up etc before joining up the the pre-cast stuff already in place.
Millwall, here we come!