26th June 2009








I love this picture!!





I'm told that 200 cubic metres of concrete is being put in the foundations today - see concrete mixer lorries in action.
The white lines on the coach park are only temporary as there is still another layer of tarmac to go on.
The "Gate House" is being installed at the coach park entrance next week.
Poppy and lorry shot for those that like that sort of thing, ie me!

19th June 2009



Double act with Barry Izbak today.
Look out for his films very soon.
He is in the poppy photo.
Coach park tarmac nearly finished as told would happen last week.
Lots of chalk from massive holes (foundations), being taken over the road.
The metal cages are honeycomb foundation reinforcements which will be placed in the bottom of the trenches, before being filled with concrete.
This will prevent subsidence, sideways movement etc of the stands.
I'm sending on a sub next week due to more globe trotting