20th February 2009



Temporary traffic lights causing chaos from Stanmer Park to Village Way due to Village Way being dug up in places for service/drainage installation.
Convuluted pipework or conduit been put in along side Village Way north side.
Site offices been moved down to a lower level.
Boning rods (in Albion blue), being banged in both sides of Village Way.

10th February 2009



Road sub-base being worked on. Now level with Village Way.
Big grey concrete pipe sections been delivered.
Bit of tree clearance on south side of Village Way, west end.
You get a better view of the scale of the works looking from the north, but you can't get good views for photos due to sun and trees.
It's really worth having a drive by, looking from the slip road up to the B2123 by the University to get a gist of the huge amount of work done so far.